A 20-year power contract can be signed today, while the new generating capacity may not arrive for years.
On September 30, 2026, Constellation and Amazon announced a 690 MW, 20-year power agreement at Calvert Cliffs. The total includes about 190 MW of new nuclear output expected between 2030 and 2032. Those are three different numbers to track: contracted power, additional capacity, and the date that extra output is expected.[2]
A power company can have rising demand, a credible customer and a signed agreement without yet recording the full earnings—or generating the cash—investors expect.
Follow the megawatts through seven gates: customer commitment, payment terms, project status, reliable delivery, capital funding, earnings timing, and cash per share.
This is a company-level due-diligence guide. For the wider question of which parts of the electricity system may benefit from AI demand, see Who Will Power the AI Boom—and Who Will Actually Profit?
First, Identify How the Business Earns Its Return
Before comparing financial results, identify the business model. Large energy companies may combine more than one of these activities, so separate the economics of each segment.
Competitive Generator
A competitive generator owns power plants and sells electricity through long-term contracts, retail supply, or wholesale power markets.
Constellation and Vistra are examples.
For this model, the important questions are usually contract price, contract length, plant reliability, fuel and operating costs, hedging, and cash flow.
Regulated Utility
A regulated utility builds and operates generation, transmission, substations, and distribution systems in a service territory.
It cannot simply raise prices whenever it spends more money.
Regulators decide which investments can be recovered from customers and what return the utility is allowed to earn.
Rate base is the value of eligible utility property on which the company is permitted to earn an approved rate of return.[1]
For this model, large data-center growth matters only when the required investment is approved, built, placed into service, and recovered under acceptable terms.
Developer or Integrated Power Company
A developer builds generation or storage projects and may sign long-term power contracts before construction is complete. An integrated company can also own utilities and generation businesses with very different revenue mechanisms.
NextEra Energy Resources, RWE, and Iberdrola operate parts of this model.
A large project pipeline can be useful, but it is not the same as a signed customer contract or an operating asset.
Question 1: Is the AI Power Demand Actually Committed?
Start with the customer commitment.
Do not treat every data-center inquiry, site discussion, or pipeline number as if it were a signed contract.
Look for:
- contracted or approved megawatts;
- contract length;
- service start date;
- customer credit quality;
- minimum-payment or take-or-pay terms;
- cancellation and delay provisions; and
- which party pays for dedicated infrastructure.
A current example shows why this matters.
On September 30, 2026, Constellation and Amazon announced a 20-year agreement supporting Calvert Cliffs in Maryland. The agreement covers 690 MW of power and supports about 190 MW of additional nuclear capacity expected to come online between 2030 and 2032.[2]
The 690 MW is the contracted power volume, not 690 MW of newly built generation. The anticipated additional output is about 190 MW, which is already included in the contract total. The agreement also supports more than $3 billion of investment across the existing plant and its continued operation.[2]
For an analyst, this creates a measurable evidence trail: named counterparty, binding commercial arrangement, power volume, incremental output, spending commitment and expected delivery date. It still does not reveal the private contract price or a guaranteed project return.
Question 2: How Does the Company Get Paid?
The same 500 MW of data-center demand can create very different economics depending on the business model.
For a Competitive Generator
Check the electricity contract.
A PPA, or power purchase agreement, is a contract for the purchase or sale of electricity over a defined period.
Record:
- contracted MW;
- price or pricing formula;
- contract duration;
- start date;
- fuel or commodity exposure;
- capacity payments or environmental attributes; and
- whether the contract supports an existing plant or requires new construction.
A long contract can improve revenue visibility. It does not guarantee a good return if operating costs, financing costs, or project costs are too high.
For a Regulated Utility
Check whether the required investment can enter rate base and earn an approved return.
In simple terms, a regulator allows the utility to recover the cost of providing service plus an approved return on eligible investment.
More eligible investment can increase allowed earnings, but a stated authorized return is not the same as an achieved return. Financing cost, construction delays, disallowed spending, and the timing of recovery all matter. Customers may also face higher bills.
This is why cost allocation has become a major issue around data centers.
Berkeley Lab’s 2026 review of large-load tariffs says utilities and regulators are increasingly using special tariffs and service agreements to manage risks such as insufficient power supply and underused investments that could otherwise affect other customers.[3]
A tariff is the official set of rates and service conditions that applies to a customer class.
Question 3: Which Milestones Are Real—and Which Are Still Pending?
Power-company presentations often show very large pipelines.
Do not put every pipeline megawatt into the same bucket.
Use five evidence stages, while checking commercial commitments and regulatory approvals separately:
- Interest: preliminary inquiries, site proposals, or unscreened pipeline.
- Negotiation: serious discussions, but key terms remain unsigned.
- Signed: a customer agreement exists; cancellation rights and conditions still matter.
- Approved / building: required regulatory permissions, financing, interconnection and construction are proceeding. Approval and contract execution are separate gates.
- Operating: the plant or connection has entered service and can begin earning under applicable terms.
NextEra Energy provides a useful example.
In Q2 2026, Florida Power & Light reported roughly 21 GW of large-load interest, with about 12 GW in advanced discussions. The company said some of that load could begin receiving service as early as 2028.[4]
Those are important demand signals.
Neither 21 GW of interest nor the 12 GW in advanced discussions should be presented as signed or operating load. The company also described about $2 billion of initial capital spending per gigawatt under its approved large-load tariff—not $2 billion of profit per gigawatt.[5]
NextEra also said that under FPL’s approved large-load tariff, it initially expects each gigawatt of large load to require roughly $2 billion of capital spending and to earn the same return on equity as other FPL investments.[5]
That statement links potential demand to a regulated investment model, but service agreements and project milestones are still needed before treating the spending or earnings as committed.
Question 4: Can the Power Plant Deliver Reliably?
A power contract has financial value only if the company can deliver electricity when required.
For nuclear and gas plants, useful operating measures include:
- capacity factor or availability;
- planned outages;
- unplanned or forced outages;
- fuel availability;
- maintenance spending; and
- license or operating life.
Capacity factor compares actual electricity production with the maximum amount the plant could have generated if it had run at full output for the entire period.
Constellation’s owned nuclear plants, excluding Salem and South Texas Project, achieved a 93.0% capacity factor in Q2 2026.[6]
That number does not tell you whether a contract is attractive, but it helps answer a different question: can the fleet actually produce electricity reliably enough to support the contracts?
For wind and solar, the operating questions are different. Check resource quality, curtailment, storage, transmission access, and contract structure.
Question 5: How Much Capital Must Be Spent Before Earnings Arrive?
Power infrastructure is capital intensive.
Before the first meaningful earnings contribution, a company may need to spend money on:
- new generation;
- plant uprates;
- transmission lines;
- substations;
- interconnection work;
- fuel infrastructure;
- storage; and
- development and permitting.
Record total project cost, construction schedule, debt, interest expense, customer advances, joint-venture funding, new shares, and expected return.
Iberdrola’s H1 2026 results show the scale of this issue. The company invested about €7 billion in the first half, with roughly 63% going to electricity networks. Its regulated network asset base reached about €55 billion.[7]
The important question is not whether the investment amount is large.
It is whether the regulated or contracted return from the new assets is high enough to compensate for the debt, equity, and execution risk required to build them.
Question 6: When Does the Contract Start Affecting Earnings?
A signed agreement can improve the long-term outlook without changing the current quarter very much.
Record three dates:
- contract signing;
- commercial operation or service start; and
- first meaningful earnings contribution.
Vistra provides a clear example.
In Q2 2026, Vistra reported ongoing-operations adjusted EBITDA of $1.767 billion and reaffirmed its 2026 guidance. Adjusted EBITDA is a company-defined measure of earnings before several costs, not the same as cash available to shareholders.[8]
Vistra said its 2026 guidance and stated 2027 opportunity range exclude the potential effects of the signed Meta agreements, some of which are expected to begin contributing to adjusted EBITDA in 2027.[8]
So a signed contract can be financially meaningful while still being mostly absent from current earnings.
Question 7: Does the Growth Reach Each Share?
Total company earnings are not the final result for a shareholder.
A large project may require debt, interest payments, new shares, or years of capital spending before it produces free cash flow.
Track:
- operating cash flow;
- free cash flow after capital spending;
- net debt;
- interest expense;
- dividends;
- share repurchases;
- new-share issuance; and
- earnings or cash flow per share.
A project can increase total EBITDA while producing only a modest benefit per share if financing costs or dilution absorb much of the value.
Dilution means that more shares are issued, reducing each existing share’s percentage ownership. New capital may create enough value to offset it, but the per-share result has to be checked.
Consider a purely illustrative example, holding everything else constant. A company’s annual free cash flow rises from $100 million to $120 million, but its share count rises from 100 million to 150 million to finance expansion.
Before: $100M / 100M shares = $1.00 FCF/share After: $120M / 150M shares = $0.80 FCF/share
Total free cash flow grew 20%, but free cash flow per share fell 20%. This is why a company-level growth headline does not finish the shareholder analysis. For capital-intensive regulated utilities, also examine the timing of capital spending and the company’s exact FCF definition.
A Seven-Field Deal Card for Quarterly Results
Keep one record for each material project or customer deal, and update the supporting evidence when the company reports.
- Demand evidence: interested MW, negotiated MW and signed MW—kept in separate columns or notes.
- Payment mechanism: contract price or pricing formula where disclosed; regulated tariff and rate-base eligibility where applicable.
- Milestones: signed date, regulatory approval, interconnection, construction status and commercial operation date.
- Deliverability: outages, capacity factor, fuel, grid constraints and other risks specific to the asset.
- Capital required: total expected CAPEX, incremental spending and who finances it.
- Earnings date: management guidance versus actual reported revenue and profit contribution.
- Per-share result: operating cash flow, defined free cash flow, net debt and diluted share count.
For each number, record the reporting period and the source document. Carrying a forecast into the next quarter without checking its status can make an unbuilt project look like an operating one.
The Question Readers Keep Asking: Who Pays If the Data Center Does Not Arrive?
This is not only an investor question. It is also a customer and regulatory question.
A utility may have to build infrastructure years before the expected data-center load is fully operating.
If the customer delays, downsizes, or cancels the project, the utility can be left with underused assets.
Berkeley Lab describes this as one of the important financial risks that large-load tariffs and electric service agreements are designed to address.[3]
Possible protections include minimum bills, contract duration requirements, customer-funded connection costs, collateral, and termination payments. The exact protections must be checked in the applicable tariff or service agreement; they are not universal.
The details matter because they determine whether project risk stays with the large customer, moves to the utility, or can affect other electricity customers.
What Changed This Quarter?
Review the same deal card each quarter. Did customer interest become a signed commitment? Did required approvals arrive? Was construction completed on schedule? Did earnings appear in the reported period? Did cash flow per share improve after financing?
The relevant progress is a change in evidence and economics—not a larger pipeline figure alone.
From a Megawatt Headline to a Cash-Flow Judgment
Start with what a company has actually secured: a signed contract, an approved tariff, a financed project, or an operating asset. Those are different stages, and each carries different uncertainty.
Then track the cash mechanism. A merchant generator relies on electricity sales and plant economics; a regulated utility needs eligible investment and timely rate recovery; a project developer needs construction discipline and contracts that support the cost of capital.
The investment case becomes stronger when a power-demand headline can be traced to a customer obligation, an achievable project, a defensible return and cash generation per share.
Continue Reading
- To understand which companies participate in the wider AI electricity supply chain, read Who Will Power the AI Boom—and Who Will Actually Profit?.
- How to Compare AI Infrastructure Stocks: 8 Numbers Investors Should Check
- Is a Big Backlog Really Good? How to Analyze Capacity in AI Infrastructure Companies
- The Grid Bottleneck Behind the AI Boom
Key Terms
- PPA: power purchase agreement, a contract for buying or selling electricity over a defined period
- rate base: eligible utility assets on which the utility may earn an approved return
- tariff: official rates and service conditions for a utility customer class
- capacity factor: actual generation compared with maximum possible generation over the same period
- pipeline: possible future projects that are not necessarily signed or operating
- commercial operation: the point when an asset begins normal revenue-producing service
- capex: capital spending used to build or improve long-lived assets
- net debt: debt minus cash and cash equivalents
- dilution: reduction in each existing share’s ownership percentage when additional shares are issued
- free cash flow: cash remaining after operating needs and capital spending under the stated definition
Sources
- FERC Glossary — rate base definition.
- Constellation / Amazon — September 30, 2026 Calvert Cliffs agreement.
- Lawrence Berkeley National Laboratory — Electricity Rate Designs for Large Loads: 2026 Update.
- NextEra Energy — Q2 2026 results.
- NextEra Energy — Q2 2026 earnings script.
- Constellation — Q2 2026 results.
- Iberdrola — H1 2026 results.
- Vistra — Q2 2026 results.
Editorial review updated October 11, 2026. Selected company filings and primary-source research were rechecked. Contract terms may be confidential, and electricity regulation differs by jurisdiction. Keep customer interest, signed agreements, regulatory approvals, construction and operating output separate when tracking projects.