Why Does a Power Grid Need Batteries That Can Set Their Own Frequency?

A battery can do more than wait for the evening price peak

When most people see a giant battery project, they ask a familiar question: how many hours of electricity can it store? Germany's newest grid-scale battery story begins there, but does not end there.

On October 14, 2026, inverter maker SMA Solar Technology announced the start of construction of a battery project at Bertikow, in Germany's Brandenburg state. Developed by ENERTRAG with partners, it is designed for 200 megawatts (MW) of power and 840 megawatt-hours (MWh) of energy storage, near a 380-kilovolt high-voltage network connection. Commissioning is targeted for 2027. SMA will provide power-conversion equipment and grid-forming controls. The launch of construction is not the same as successful operation or proven performance. SMA's official announcement.

The unusual point is not the size alone. It is that the battery is being equipped to help support the voltage and frequency behavior of the electricity grid, rather than only moving electricity between cheap and expensive hours.

Batteries can sell electricity at a useful time. With the right controls, they may also help keep the electricity system usable in the first place.

First understand the two numbers: 200 MW and 840 MWh

MW measures how quickly the battery can deliver or absorb electrical power at one moment. MWh measures an amount of energy. Think of power as the rate at which water leaves a tank and energy as the amount stored inside. The analogy is useful, though electrical engineering involves additional constraints.

A simple calculation for Bertikow is:

840 MWh ÷ 200 MW = 4.2 hours.

That is the theoretical time to discharge the full rated energy at rated power. It ignores operating reserves, charging/discharging losses, temperature, degradation, inverter restrictions and contractual settings. It is not a guarantee of 4.2 hours at the grid connection every day.

The same battery could theoretically supply 100 MW for 8.4 hours if every other condition stayed ideal. The power and energy are still linked. But neither 200 MW nor 840 MWh tells us how well the equipment reacts to a grid disturbance in the first few fractions of a second.

Figure 1. Bertikow’s announced ratings imply 840 MWh / 200 MW = 4.2 hours of ideal rated discharge, not a guaranteed delivered run time.
Figure 1. Bertikow’s announced ratings imply 840 MWh / 200 MW = 4.2 hours of ideal rated discharge, not a guaranteed delivered run time.

The hidden problem: electricity must stay synchronized

In most European power networks, alternating-current electricity oscillates at a nominal 50 hertz (Hz). That means the waveform cycles 50 times each second. Large disturbances and imbalances between generation and consumption can push system frequency away from that reference. Voltage also has to remain within acceptable limits.

Traditional large generators contain rotating machines synchronized to the grid. The rotation stores kinetic energy and contributes to what engineers call inertia: resistance to sudden changes in frequency. Other generator and control systems also regulate voltage and provide reserves. Inertia is not the same as the energy stored in a battery, and none of these contributions makes a power system immune to outages.

Solar panels and batteries use direct current (DC) internally. To send alternating current to the grid, they require an inverter, a power-electronics device that turns DC into controlled AC. As more electricity passes through inverters instead of conventional rotating generators, the grid needs to maintain stable voltage and frequency using a different mix of equipment and controls.

Following the grid and forming the grid are different jobs

A typical grid-following inverter observes an existing AC waveform, synchronizes with its voltage and phase, and injects current at the appropriate time. It is like a musician listening to the orchestra's beat. It needs a sufficiently reliable external reference. This does not mean every grid-following inverter lacks frequency-response features; rather, its core synchronization approach depends on the existing grid.

A grid-forming inverter actively establishes and regulates a voltage waveform and frequency reference through its controls, like a musician able to help establish the beat. A properly designed and coordinated system can respond rapidly to disturbances and help maintain stable conditions even with fewer traditional spinning generators online. It is not simply a battery declaring that the entire European grid will now operate at a frequency of its choosing: many machines and control systems have to synchronize and coordinate.

At Bertikow, SMA says it plans 29 medium-voltage power stations, each accommodating two battery inverters, with redundant plant managers and a dedicated Synchronous Grid Forming Package. This is a specified design configuration, not publicly verified proof that every planned grid service has already passed field tests. SMA detailed project description.

Figure 2. Simplified concept: grid-following control uses an existing AC waveform; grid-forming control helps establish and regulate one. Neither automatically qualifies for every grid service.
Figure 2. Simplified concept: grid-following control uses an existing AC waveform; grid-forming control helps establish and regulate one. Neither automatically qualifies for every grid service.

What happens in the first seconds after a problem?

Imagine a large generator unexpectedly disconnecting. Supply suddenly falls short of demand and grid frequency tends to decline. Different services act over different timescales.

Inertial response acts very quickly, opposing the initial rate of frequency change. A rotating generator naturally releases some kinetic energy as its speed changes. A grid-forming battery inverter can be designed to provide a controlled, inverter-based response, sometimes called synthetic or virtual inertia, by using its power electronics and available energy/power headroom.

Frequency containment reserve (FCR) then helps arrest frequency deviation using automatically activated reserves. Other balancing mechanisms can restore the system closer to normal over longer timescales. These are related but not identical products. A device able to form voltage does not automatically qualify for inertia procurement, FCR, voltage support and black start at once.

Black start, the process of restarting parts of a grid after a widespread blackout without external grid power, is yet another capability. Certain grid-forming systems may support it under the right engineering conditions, but it would be wrong to claim the Bertikow project already has an approved black-start contract. U.S. national-laboratory guidance discusses the testing challenges of inverter-driven black start. National laboratory technical overview.

Germany is beginning to pay for a different kind of battery value

Historically, a common battery business model was energy arbitrage: charge when electricity is inexpensive, discharge and sell when it is expensive. Another revenue stream comes from balancing services, where grid operators pay eligible resources to hold capacity or respond to a change in frequency.

Germany took an important step in January 2026 by opening market-based procurement for instantaneous reserves, sometimes called Momentanreserve, which can be supplied by suitable grid-forming equipment. The German federal economic ministry says this creates a route for inverter-based systems to provide a service traditionally associated with large conventional generators. German government explanation.

The four German transmission system operators publish product requirements and fixed prices denominated in euros per MW-second per year (€/MWs/year) for this service. That unusual unit reflects an inertia-related service, not ordinary energy bought in euros per MWh. It is not a rate that can simply be multiplied by Bertikow's 200 MW or 840 MWh to determine its annual revenues. A verified qualifying response, accepted technical certification, contracted quantities, measurement rules and actual commercial participation all matter. German TSO procurement documentation.

This is the economic change worth watching: the market is learning to pay not only for electricity delivered, but also for the technical ability to keep the network stable.

Can one battery earn money in several markets at once?

Potentially, but not without trade-offs. A storage operator could consider wholesale price spreads, FCR, other balancing reserves and newer stability products. Yet the same inverter and battery have finite power, current, energy, state-of-charge range and short-term overload capability. Different commitments may overlap or conflict.

A battery committed to reserve capacity cannot always use every available megawatt for profitable wholesale dispatch. A grid-forming installation may also need extra controls, power-electronics headroom, engineering tests and certification. Therefore a projected revenue stream must be reduced by the cost and operational opportunity cost of providing it. A grid-forming label is not a guaranteed extra profit margin.

Bertikow's announced capacity and planned technology can establish what developers hope to build; the public materials reviewed do not establish the final project CAPEX, a guaranteed annual stability-service payment, or actual margins once the system starts operating.

Does this solve renewable curtailment as well?

Batteries can help absorb surplus solar or wind generation and deliver electricity later. Bertikow's location near a high-voltage grid node is relevant for using that flexibility. But energy shifting is not identical to voltage- and frequency-forming support.

A battery can be in the wrong location to solve congestion elsewhere, it can already be full, and four-ish hours of nominal storage cannot cover every multi-day wind drought. Grid-forming capability does not create additional stored MWh, nor does it increase the physical capacity of distant power lines.

Our earlier article looks at the separate question of why renewable electricity must sometimes be turned down: https://www.thecontexta.com/2026/08/renewable-energy-curtailment-explained.html.

Five questions to ask when a big battery project is announced

  1. What is the rated power (MW)? This measures the pace of charging or discharging, not the stored amount.
  2. How much energy can it store (MWh)? Divide by rated MW for a theoretical discharge duration, with caveats.
  3. Is it grid-following or grid-forming? Look for a specific inverter control system and test evidence, not an advertising label alone.
  4. Which stability service is it qualified to sell? Inertia, FCR, voltage support and black start involve distinct obligations and technical tests.
  5. Where does the money come from? Wholesale arbitrage, availability payments, balancing payments and stability contracts have different risks and cost consequences.

Before January's reform, a grid-forming capability might have been difficult to monetize directly in Germany. The emergence of published procurement rules begins to change that, but the grid service must be technically demonstrated and economically contracted. Battery specifications are turning into an infrastructure and market-design question.

The next structural question

A renewable electricity system needs both energy that can be moved through time and the ability to hold a stable electrical reference while doing so. Bertikow is a useful example because its storage volume is not the whole story.

When batteries help replace a stabilizing function once supplied by large rotating generators, how should the market measure and pay for that function?

Key Terms

  • MW (megawatt): A unit of power—the instantaneous rate of electricity transfer.
  • MWh (megawatt-hour): A unit of energy, equal to using one MW continuously for one hour.
  • Grid-following inverter: A power converter that synchronizes with an existing AC grid reference.
  • Grid-forming inverter: A power converter designed to establish and regulate an AC voltage/frequency reference in coordination with a wider power system.
  • Inertia / instantaneous reserve: A fast stabilizing response that resists a sudden frequency change; not the same as stored energy or standard frequency reserves.
  • FCR: Frequency Containment Reserve, an automatically activated reserve service to limit frequency departures.
  • Black start: Restoration of part of a power grid without relying on an energized outside grid.
  • Energy arbitrage: Buying or storing energy when prices are lower and selling when prices are higher.

Sources and verification

  1. SMA Solar Technology — Bertikow project announcement, October 14, 2026.
  2. SMA — Grid-forming certification announcement, September 28, 2026.
  3. German Federal Ministry — New instantaneous reserve procurement, 2026.
  4. German transmission operators — Market-based procurement of inertia, 2026–27.
  5. NREL — Technical Roadmap for Grid-Forming Inverters.
  6. U.S. DOE — Powering On with Grid-Forming Inverters.
  7. National Laboratory — Black-start technical overview.

Research cutoff: October 17, 2026. Bertikow is under construction; its 2027 commissioning date is a target. The 4.2-hour calculation is an ideal rating quotient. No project-specific market revenue or black-start qualification is asserted.